Introduction
The System Engineering Methodology is documented in several OOI CI documents, including the CI System Life Cycle.
Engineering Process and Plan Overviews
A brief summary:
- There are 5 Releases in the 5-year development project: Data Distribution Network, Managed Instrument Network, OnDemand Measurement Processing, Integrated Modeling Network, Interactive Ocean Observatory.
- There are 4 Phases in each Release: Inception, Elaboration, Construction, Transition.
- There are 2 or 3 Iterations in each of the first 3 Phases.
- There are 3 Periods in each 8-week Iteration: Design Period, Development Period, Wrap-Up Period.
Spiral Development Model
- Phases
- Review Milestones Process (see here for actual reviews conducted)
- Life Cycle Objectives Review
- Life Cycle Architecture Review
- [Initial Operational Capability Review]
- Product Readiness Review + Functional Configuration Audit
- References
Iteration Structure
- Iteration Structure Description: Composition of an 8-Week Iteration
- Design Period Activities
- Development Period Activities
- Wrap-Up Period Activities
(view as slideshow)
Reqirements Process Graph Hierarchy of Engineering Aritfcats User Requirements Elicitaton Process Engineering Process Overview
Engineering Roles, Responsibilites and Artifacts Integrated Observatory Network Release Schedule Integrated Observatory Network Subsystem Release Schedule Spiral Development MOdel