OOI Cyberinfrastructure Development
This is the homepage describing construction for the Ocean Observatories Initiative Cyberinfrastructure (OOI CI), including any preceding activities and prototype development.
Quick Hits
- New Developers: Here's the developers tutorial and the developers environment.
- New Developers Guide to JIRA Task Management
- Development Team Meetings
- CI Development Calendar - events and meetings for CI developers
- LCAARCH Development Project
- CI Travel Request Approval Page
- CI Development Recently Updated pages
- CI Team Rosters
Cyberinfrastructure Release 1
The OOI Cyberinfrastructure project Construction award commenced October 12, 2009 and will continue through the summer of 2014.
The CI deliverables will be developed and deployed across five releases. Release 1 will be deployed into production March 2011.
Each release has 7 iterations of 8 weeks duration. Iterations 1 and 2 make up the Inception phase, leading to the Life Cycle Objectives (LCO) milestone review; iterations 3 and 4 make up the Elaboration phase, leading to the Life Cycle Architecture (LCA) milestone review; iterations 5, 6 and 7 make up the Construction phase, leading to Initial Operating Capability (IOC) and review. The subsequent Transition phase brings the fully integrated release into operations. The subsequent Release's Inception phase begins towards the end of the Construction phase of the preceding Release.
Activities (by topic)
- Design Team, System Architecture Refinement
- Subsystems Development (COI, CEI, DM, S&A and later A&S and P&P)
- System Implementation (Instrument and Platform Agents IPAA, Terrestrial CyberPoPs/Network, External Observatory Integration)
- CI Integration, Test, and Verification
- Product Specifications
- CI Milestones and Review Events
Activities (by time)
- Inception Phase
- Inception Phase Iteration 1 (Oct 12 to Dec 2, 2009)
- Iteration 1 Design Period (Oct 12 to Oct 23, 2009)
- Subsystem R1 I1 Design Period Report
- Wrap-Up Reviews
- Teams
- Inception Phase Iteration 2 (Dec 3 to Feb 11)
- Iteration 2 Design Period (Dec 3 to Dec 16, 2009)
- Inception Phase Iteration 1 (Oct 12 to Dec 2, 2009)
- Life Cycle Objectives (LCO) Review (Feb 12 to Feb 26)
- Elaboration Phase
- Elaboration Coordination
- Elaboration Phase Iteration 1
- Elaboration 1 Design Period (March 8 to March 19)
- Elaboration Phase Iteration 2
- Elaboration 2 Design Workshop (May 2010 at UCSD)
- Wrap-Up Reviews
- Elaboration Phase Iteration 3
- Elaboration 3 Design Period (June 21 - July 2)
- Life Cycle Architecture (LCA) Review (August 24-25)
- Construction Phase
- Construction Phase Iteration 1
Developer Knowledge Base
- Background Materials provides references to selected background materials
New developers tutorial- Technology Research
OOI CI Development Team Organization
- Project Infrastructure
- Software Development Environment
- System Administration
- Integration, Test and Verification
- Meetings and Events
Cyberinfrastructure Construction Start
The OOI program started in September 2009 with the CI construction effort commencing in early October 2009. The OOI CI partnership is holding its team meeting to finalize plans and coordinate the details associated with Release 1 - "Data Distribution Network" outside Boulder CO in early September.
- OOI CI Kick-Off Meeting, Sept 9-11, 2009, summarizing progress on the designs and prototype investigations to date and finalize construction plans
Pre-Construction Prototype Investigations
The emphasis of OOI CI development during the pilot period (Jan 2009 continuing through Dec 2009) was on risk reduction through prototyping and on getting ready for construction. Many of the prototype projects follow a 6 week iteration cycle.
- Overview of Prototypes: Table listing OOI prototypes and their descriptions
- Prototypes Integration and Dependencies (historical)
- The Prototypes are targeted to reduce the Selected Notes from CI Risk Management Plan that complex components of the OOI pose to the system functionality
- Pilot period Prototypes:
Agent Contract Network,Cloud Provisioning Environment,Collaboration Tools,Data Distribution Network Version 1, Data Exchange,Global Load Balancing,Messaging Service,OMF Collaboration,OSSE,Semantic Framework Integration Prototype,SQLstream Prototype,Unstructured Grid Services (with Hyrax integration) and others - Activities: Field Deployment of the OSSE (Observing System Simulation Experiment) prototype, Nov 2-13 2009, mid-Atlantic Bight