Release 1
Inception Phase
Iteration 1
- Design Period: 10/12/09 - 10/23/09
- Development Period: 10/26/09 - 11/25/09 Note: Thanksgiving holidays shorten the period
- Wrap-up Period: 11/30/09 - 12/02/09. Note: Switch to Wed COB between periods
Iteration 2
- Design Period: 12/03/09 - 12/16/09
- Development Period: 12/17/09 - TBD. Note: Holidays (2 weeks) interrupt the period.
- Wrap-up Period
Life Cycle Objective (LCO) Milestone and Review
- Preparation
- Review
- Analysis and Report
Elaboration Phase
Iteration 3
- Design Period
- Development Period
- Wrap-up Period
Iteration 4
- Design Period
- Development Period
- Wrap-up Period
Life Cycle Architecture (LCO) Milestone and Review
- Preparation
- Review
- Analysis and Report
Construction Phase
Iteration 5
- Design Period
- Development Period
- Wrap-up Period
Iteration 6
- Design Period
- Development Period
- Wrap-up Period
Iteration 7
- Design Period
- Development Period
- Wrap-up Period
Initial Operating Capability (IOC) Milestone and Review
- Preparation
- Review
- Analysis and Report
Transition Phase
|